Alderwood Water board was scheduled to weigh recoating contract for Nike reservoirs
Materials published ahead of the May 5, 2025, board meeting showed Alderwood Water & Wastewater District staff proposing approval of a contract to recoat Nike Reservoirs 1 and 2. 1
What the records say
Alderwood Water & Wastewater District (AWWD) staff were scheduled to ask the Board of Commissioners to approve a contract award for recoating Nike Reservoirs 1 and 2. The item appeared on the board's May 5, 2025, agenda under unfinished business, brought by Capital Program Manager Don Ranger and Project Engineer David MacDonald. 1
- The AWWD Board of Commissioners agenda for May 5, 2025, listed approval of a contract award for recoating Nike Reservoirs 1 and 2 (project W2313) as an action item under unfinished business. 1
- The item was presented by the Capital Program Manager and the Project Engineer, indicating a capital-maintenance project. 1
- The pre-meeting record does not include the contract amount, the selected contractor, or a work timeline. 1
Why it matters
Recoating a reservoir is maintenance work that protects the water storage tanks from corrosion and extends their useful life, which helps keep the drinking-water system reliable. The agenda does not say what the contract would cost or when the work would happen, so residents cannot yet see the financial details from this record. 1